Concrete may have
Ships were lost du
Once considered th
Ships were lost du
Chapter 1. Our st
Chapter 1. Our st
Chris! I told you
Ships were lost du
Stop dancing like
Chapter 1. Once Once considered the most complex solution, we are now driven by
new data to conclude the simpler explanation is the correct one. The data
suggests the increase in heating demand over the last decade has not been
matched by a proportional increase in heating capacity. Although there has
been some slight increase in capacity, it is not enough to meet the
additional demand. As the end of the decade approaches, this mismatch
between demand and supply will become more and more stark. Based on this
analysis, we have concluded that neither an upgrade of the current pipeline
systems nor the construction of new transmission lines is a sustainable or
desirable option for the future.
The situation is particularly acute for Eastern Canadian Gas Transmission,
which is a single line from the Alberta/Saskatchewan Border to New York.
This line is currently being used at around half of its capacity. Because of
the line,s limited capacity, the delivery point is limited to the AECO area.
Based on the foregoing, we have created a detailed project schedule to act as
a guide for the entire project. However, given the number of variables in
the proposal, it is likely that the project will require more detailed
information to proceed further at this time.
Efforts to obtain a greater level of understanding must be coordinated
between TransCanada, National Energy Board (NEB), Federal Agencies, US &
Canadian Governments, and other potential partners and stakeholders. As you
will see, the project schedule is complex and requires a significant amount
of work for the next three months.
We are looking forward to working with you, and if you have any questions or
require additional assistance please do not hesitate to contact myself, Rob
Waugh, Leslie Lawner, John Novak or Jeff Keeler.
Thank You,
W. J. (Billy) Wilson, Jr.
Director, CA Development
---------------------- Forwarded by William J Haizmann/HOU/EES on 12/07/2000
05:40 PM ---------------------------
Enron Energy Services
From: Susan Scott @ EES 12/06/2000 01:29 PM
Phone No: 713 853-0596
To: Billy Lemmons/Corp/Enron@ENRON, Brad Pettinger/HOU/EES@EES, Dave
Schafer/NA/Enron@ENRON, Jeff Dasovich/NA/Enron@Enron, James E
Keller/HOU/EES@EES, Wanda Curry/HOU/EES@EES, Evan Hughes/HOU/EES@EES, Doug
Sewell/HOU/EES@EES, David K Mack/ENRON_DEVELOPMENT@ENRON_DEVELOPMENT, David
Nutt/Corp/Enron@ENRON, Greg Blair/Corp/Enron@Enron, Harry Kingerski/NA/Enron@Enron
cc: Tom Riley/Western Region/The Bentley Company@Exchange, Ken
Frankel/HOU/EES@EES, Jeff Golden/HOU/EES@EES, John
Shafer/OTS/Enron@Enron, Chuck Webb/HOU/EES@EES, David P Vos/HOU/EES@EES
Subject: Preliminary 2001 Integrated Production/Cost Estimate
Attached is an estimate of combined production and cost for new and
continued projects for 2001. This estimate is based on the decisions that
Enron's west business units have made regarding new projects and
approximately 60 percent of the corporatewide projects that will be completed
next year. This work will be coordinated with the individual project
schedules that are under way throughout Enron.
Although this schedule was formulated with the assumption that successful
completion of all corporate projects will be guaranteed, there is too much
uncertainty surrounding the projects and costs to be certain of the actual
costs. In addition, the level of any increase in the price of oil, LNG or
other commodities this year will also significantly impact the 2001
schedule. Therefore, this schedule is only an estimate of Enron's potential
costs. The final schedule and costs will be formulated when the individual
project schedule are finalized throughout Enron.
Please keep this schedule confidential.
Susan Scott
Transwestern Pipeline Company
P.O. Box 1738
Houston, TX 77251
Susan.Scott@enron.com